Show/Hide

 Debris Collection Hotline (239) 252-8444. FEMA Disaster Recovery Center open in

Collier County

Growth Management Plan Amendments

Print
Press Enter to show all options, press Tab go to next option

Transmittal & Adoption Cycles

INTRODUCTION

This process details the discrete steps taken to support the Growth Management Plan process. The purpose of the Growth Management Plan (GMP) is to maintain the State of Florida required comprehensive long range plan for Collier County. The GMP petitions are processed three times a year by being submitted to the transmittal and adoption evaluation process. These processes include recording the research information for the specific GMP elements, the staff’s analysis, petition hearing by the Collier County Planning Commission and the Board of County Commissioners, notifying the public, and reviews by several state department/agencies.

ALL PREVIOUSLY PROCESSED GROWTH MANAGEMENT PLAN AMENDMENTS MAY BE FOUND UNDER THE ARCHIVE PAGE SECTION LISTED TO THE LEFT IN "WHITE FONT".  SHOULD YOU NOT BE ABLE TO FIND WHAT YOU ARE LOOKING FOR, PLEASE CONTACT THE WEBMASTER VIA THE LINK PROVIDED:

 TO REQUEST A GMP AMENDMENT PRE-APPLICATION MEETING:
CLICK HERE

Preapplication Fee $500.00
(9 month cut off for application submittals - a new pre-application meeting is required if beyond)

Pre-application GMPA standard comments
(updated July 2015)

GMPA: Application Form

Growth Management Division Fee Schedule (effective 10/01/2015)
   
AGENDA's MAY BE FOUND ON CCPC & BCC SCHEDULED HEARINGS PAGE: 

CLICK HERE:  http://www.colliergov.net/Index.aspx?page=3331 

*** *** ***

2017 GMP AMENDMENT SUBMITTALS:
Last Friday of February, June & October

TO CHECK STATUS OF A GROWTH MANAGEMENT PLAN AMENDMENT PROJECT:

GMP Amendments ay be monitored via the new Portal
[Note: you must use the assigned PL # in order to access]
(Example: PL20110000XXXX)
Click here: 

     http://cvportal.colliergov.net/cityviewweb


SCHEDULED HEARINGS:
 

 ***********

COLLIER COUNTY PLANNING COMMISSION MEETING
NOVEMBER 16, 2017 – ADOPTION HEARING
GROWTH MANAGEMENT PLAN AMENDMENT
LOGAN BLVD./IMMOKALEE ROAD COMMERCIAL INFILL SUBDISTRICT 
PL20160001100/CP-2016-2


ADOPTION ADVERTISEMENT:

As the advertisement as it will appear in the Naples Daily News on October 27, 2017.

ADOPTION STAFF REPORT: 
PL20160001100/CP-2016-2 

ADOPTION ORDINANCE: 
PL20160001100/CP-2016-2 

TRANSMITTAL EXECUTIVE SUMMARY:
PL20160001100/CP-2016-2

TRANSMITTAL ADDENDUM STAFF REPORT:

PL20160001100/CP-2016-2

TRANSMITTAL STAFF REPORT
:
PL20160001100/CP-2016-2

NIM MEETING NOTES:
PL20160001100/CP-2016-2

TRANSMITTAL RESOLUTION:
PL20160001100/CP-2016-2

ADOPTION PROJECT APPLICATION: Pending
PL20160001100/CP-2016-2

 

AND

COLLIER COUNTY PLANNING COMMISSION MEETING
NOVEMBER 16, 2017 – TRANSMITTAL HEARING
GROWTH MANAGEMENT PLAN AMENDMENT
PINE RIDGE COMMONS MIXED-USE INFILL SUBDISTRICT
PL20160002360/CP-2016-3
 
 

 

TRANSMITTAL ADVERTISEMENT:
As it will appear in the Naples Daily News on October 27, 2017

TRANSMITTAL STAFF REPORT: PENDING

PL20160002360/CP-2016-3

TRANSMITTAL RESOLUTION: PENDING
PL20160002360/CP-2016-3

TRANSMITTAL PROJECT APPLICATION: PENDING
PL20160002360/CP-2016-3 

***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***  ***  

COLLIER COUNTY PLANNING COMMISSION MEETING
OCTOBER 5, 2017 – ADOPTION HEARING
VANDERBILT BEACH/COLLIER BLVD. COMMERCIAL SUBDISTRICT
GROWTH MANAGEMENT PLAN AMENDMENT
PL20150002167/CP-2015-2
[CONTINUED TO OCTOBER 19, 2017]

Approved 7-0  

CCPC ADOPTION ADVERTISEMENT: Continued on 9/21/2017 and 10/5/2017
As the advertisement appeared in the Naples Daily News on September 01, 2017.

ADOPTION STAFF REPORT:
PL20150002167/CP-2015-2

ADOPTION ORDINANCE: 
PL20150002167/CP-2015-2

TRANSMITTAL EXECUTIVE SUMMARY:
PL20150002167/CP-2015-2

TRANSMITTAL STAFF REPORT:
PL20150002167/CP-2015-2

NIM MEETING NOTES
PL20150002167/CP-2015-2

TRANSMITTAL RESOLUTION
PL20150002167/CP-2015-2

ADOPTION PROJECT APPLICATION/PL20150002167/CP-2015-2:

Part I
Part II

***   ***   ***   ***   ***   ***   ***   ***   ***   *** 

Department of Economic Opportunity - Notice of Intent to find Batch #2 Amendments in compliance
BCC Approval 5-0, to
Transmit the Adopted Amendments to the Department of Economic
Opportunity (DEO) 

Ordinance 2017-20 (CCME), 2017-21 (CIE), 2017-22 (FLUE), 2017-23 (GGAMP), 2017-24 (Stormwater Sub
element of the Public Facilities Element),
and 2017-25 TE)

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
JUNE 13, 2017 - ADOPTION HEARING
IN-HOUSE BATCH #2 GMP AMENDMENTS 
PL20130002637/CPSP-2013-11

BCC Advertisement as it will appear on May 24, 2017
PL20130002637/CPSP-2013-11 

ADOPTION EXECUTIVE SUMMARY:
PL20130002637/CPSP-2013-11 

ADOPTION STAFF REPORT:
PL20130002637/CPSP-2031-11

CONSERVATION AND COASTAL MANAGEMENT ELEMENT ADOPTION ORDINANCE:
PL2030002637/CPSP-2013-11

CAPITAL IMPROVEMENT ELEMENT ADOPTION ORDINANCE:
PL20130002637/CPSP-2013-11

FUTURE LAND USE ELEMENT ADOPTION ORDINANCE:
PL20130002637/CPSP-2013-11 

GOLDEN GATE AREA MASTER PLAN ELEMENT ADOPTION ORDINANCE:
PL20130002637/CPSP-2013-11 

STORMWATER MANAGEMENT SUBELEMENT OF THE PUBLIC FACILITIES ELEMENT:
ADOPTION ORDINANCE: PL20130002637/CPSP-2013-11 

TRANSPORTATION ELEMENT ADOPTION ORDINANCE:
PL20130002637/CPSP-2013-11 

ADOPTED TRANSMITTAL RESOLUTION:
PL20130002637/CPSP-2013-11

TRANSMITTAL EXECUTIVE SUMMARY:
PL20130002637/CPSP-2013-11

TRANSMITTAL STAFF REPORT ADDENDUM:
PL20130002637-CPSP-2013-11

TRANSMITTAL STAFF REPORT:
PL20130002637/CPSP-2013-11

***    ***    ***    ***    ***    ***    ***    ***        

BOCC Approval 5-0, to Transmit to the Department of Economic Opportunity (DEO) 
Ordinance No. 2017-87 

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
MAY 09, 2017 - TRANSMITTAL HEARING
IMMOKALEE ROAD/LOGAN BLVD. COMMERCIAL INFILL SUBDISTRICT
PL20160001100-CP-2016-2
 
CCPC Advertisement as it appears in the Naples Daily News on April 19, 2017:
PL20160001100/CP-2016-2

EXECUTIVE SUMMARY: 
PL20160001100/CP-2016-2

STAFF REPORT ADDENDEM:
PL20160001100/CP-2016-2

STAFF REPORT:
PL20160001100/CP-2016-2

NIGHT INFORMATION MEETING MINUTES:
PL20160001100/ P-2016-2

TRANSMITTAL RESOLUTION:
PL20160001100/CP-2016-2

APPLICATION/PETITION:
PL20160001100/CP-2016-2

***    ***    ***    ***    ***    ***   ***

CCPC Recommendation to BCC to transmit to the Dept. of Economic Opportunity (DEO)
6
-0

COLLIER COUNTY PLANNING COMMISSION
APRIL 20, 2017 - ADOPTION HEARING
BATCH #2 IN-HOUSE GMP AMENDMENTS
PL20130002637-CPSP-2013-11

CCPC Advertisement as it appears in the Naples Daily News on March 31, 2017
PL20130002637/CPSP-2013-11

PROJECT GMP AMENDMENT CCPC HEARING PACKET:
(
includes Transmittal backup documents) PL20130002637-CPSP-2013-11  

 
***      ***      ***      ***      ***    ***

CCPC Recommendation to BCC to transmit to the Dept. of Economic Opportunity (DEO)
6
-0

COLLIER COUNTY PLANNING COMMISSION
APRIL 20, 2017 - CCPC CONSENT OF 4/06/2017 
TRANSMITTAL HEARING PL20160001100/CP-2016-2

Revision to Resolution Exhibit "A" Text Changes:
PL20160001100/CP-2016-2

****    ****    ****    ****    ****    ****    ****   ****    ****   

Approved 4-1 Recommended to transmit to DEO & State Agencies: 
Letter to DEO - PL20150002167/CP-2015-2

Adopted Resolution:
PL2015002167/CP-2015-2

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
APRIL 11, 2017 - TRANSMITTAL HEARING
VANDERBILT BEACH ROAD  & CR951 (Collier Blvd.)
PL20150002167-CP-2015-2

BCC Advertisement as it appears in the Naples Daily News on March 22, 2017  
PL20150002167/CP-2015-2

EXECUTIVE SUMMARY:
PL20150002167/CP-2015-2

TRANSMITTAL (BCC) RESOLUTION w/EXHIBIT "A":
PL20150002167/CP-2015-2

CCPC TRANSMITTAL "DRAFT" MINUTES OF MEETING:
PL20150002167/CP-2015-2

Note:  All other related documents may be found below under Collier County Planning Commission
          Meeting - February 16, 2017.
 

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***   *** 
CCPC Recommendation to the BCC: Vote 7-0 to Transmit to the Department
of Economic Opportunity (DEO)

COLLIER COUNTY PLANNING COMMISSION
APRIL 06, 2017 - TRANSMITTAL HEARING
IMMOKALEE ROAD & LOGAN BLVD.
PL20160001100/CP-2016-2

CCPC Advertisement as it appears in the Naples Daily News on March 17, 2017: 
PL20160001100/CP-2016-2

PROJECT/PETITION GMP APPLICATION CCPC PACKET:  
PL20160001100/CP-2016-2

ADDENDUM STAFF REPORT:
PL20160001100/CP-2016-2

*** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** 

COLLIER COUNTY PLANNING COMMISSION MEETING
FEBRUARY 16, 2017 – TRANSMITTAL HEARING
VANDERBILT BEACH ROAD & CR951 (Collier Blvd.)
PL20150002167/CP-2015-2

 Recommendation to BCC to transmit to DEO - 4-1 w/conditions 

CCPC TRANSMITTAL ADVERTISEMENT:
The advertisement as it appears in the Naples Daily News on January 27, 2017.

CCPC TRANSMITTAL STAFF REPORT:
PL20150002167/CP-2015-2

NIGHT INFORMATION MEETING (NIM) NOTES:
PL201500-02167/CP-2015-2

LETTERS OF OBJECTION: [Due to the size, the document has been split into batch sections, below]
Batch 1
Batch 2
Batch 3
Batch 4
Batch 5
Batch 6
Batch 7

TRANSMITTAL (CCPC) RESOLUTION w/EXHIBIT “A” :
PL20150002167/CP-2015-2

PROJECT/PETITION GMP APPLICATION:
PL20150002167/CP-2015-2
 
***  ***  ***  ***  ***  ***  ***  ***  ***  ***  ***  ***  ***  ***  ***  ***  ***  ***  ***  *** *** ***

Approved 5-0 Recommended to transmit to DEO & State Agencies:
Letter to DEO

This document is rather large and may take several moments to open:
Adopted Transmittal Resolution #2016- 280 

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
TRANSMITTAL HEARING
BATCH #2 GMP AMENDMENTS
PL20130002637/CPSP-2013-11

BCC TRANSMITTAL ADVERTISEMENT:
As it appeared in the Naples Daily News on November 26, 2016  

BCC TRANSMITTAL EXECUTIVE SUMMARY:
PL20130002367/CPSP-2013-11

BCC TRANSMITTAL RESOLUTION w/EXHIBIT A's:
PL20130002637/CPSP-2013-11 

***   ***   ***   ***  ***   ***   ***   ***   ***   ***   ***   ***   *** 

CCPC RECOMMENDATION TO BOCC TO APPROVE WITH MINOR CONDITIONS - 5-0 

COLLIER COUNTY PLANNING COMMISSION MEETING
TRANSMITTAL HEARING
[continued from June 16, 2016 & July 07, 2016 & re-advertised for October 20, 2016]
BATCH #2 GMP AMENDMENTS
PL20130002637-CPSP-2013-11


CCPC TRANSMITTAL RE-ADVERTISEMENT:
As it will appear in the Naples Daily News on September 30, 2016

CCPC TRANSMITTAL ADVERTISEMENT:
As it appeared in the Naples Daily News on May 27, 2016

CCPC TRANSMITTAL ADDENDUM STAFF REPORT: 

PL20130002637/CPSP-2013-11 

CCPC TRANSMITTAL STAFF REPORT:  

PL20130002637-CPSP-2013-11

REVISED TRANSMITTAL RESOLUTION w/Exhibit A's: 
PL20130002637/CPSP-2013-11

INITIAL TRANSMITTAL RESOLUTION w/EXHIBIT A’s:
PL20130002637-CPSP-2013-11 ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***
Adopted - BCC 5-0 to transmit to the Department of Economic Opportunity (DEO)

Cover Letter to the Department of Economic Opportunity (DEO)

Adopted Ordinance No. 2016-15


COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
MAY 24, 2016 - ADOPTION HEARING
SMALL SCALE GROWTH MANAGEMENT PLAN AMENDMENT
DAVIS BLVD./RADIO ROAD COMMERCIAL SUBDISTRICT
PL20150002541/CPSS-2015-4 (companion RZ-PL20140002642)

BCC EXECUTIVE SUMMARY:
PL20150002541/CPSS-2015-4

CCPC ADOPTION STAFF REPORT
PL20150002541/CPSS-2015-4

ADOPTION ORDINANCE w/EXHIBIT “A’s”:
PL20150002541/CPSS-2015-4

PETITION: PL20150002541/CPSS-2015-4:

Part I

Part II
***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***
Adopted - BCC 5-0 to transmit to the Department of Economic Opportunity (DEO):

Cover Letter to the Department of Economic Opportunity (DEO)

Approved Ordinance 2016-12

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS 
SMALL SCALE GROWTH MANAGEMENT PLAN AMENDMENT
NAPLES BRIDGE CENTER - ADOPTION HEARING
PL20150002525/CPSS-2015-3 [companion CU-PL20150000873]

BCC ADOPTION ADVERTISEMENT:
As it appeared in the Naples Daily News on April 20, 2016

BCC EXECUTIVE SUMMARY:
PL20150002525/CPSS-2015-3

CCPC STAFF REPORT:
PL20150002525/CPSS-2015-3

ORDINANCE:
PL20150002525/CPSS-2015-3

COMPLETE BCC HEARING PACKET:
PL20150002525/CPSS-2015-3 

****   ****    ****    ****   ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    **** 

Recommended by CCPC 6-0 on  05/05/2016 to forward to BCC 05/24/2016

COLLIER COUNTY PLANNING COMMISSION MEETING
MAY 05, 2016 - ADOPTION HEARING
SMALL SCALE GROWTH MANAGEMENT PLAN AMENDMENT
DAVIS BLVD./RADIO ROAD COMMERCIAL SUBDISTRICT
PL20150002541/CPSS-2015-4 (companion RZ-PL20140002642)

CCPC ADOPTION ADVERTISEMENT:
As it appeared in the Naples Daily News on April 15, 2016

CCPC ADOPTION STAFF REPORT
PL20150002541/CPSS-2015-4

ADOPTION ORDINANCE w/EXHIBIT “A’S”:
PL20150002541/CPSS-2015-4

PETITION: PL20150002541/CPSS-2015-4

Part I

Part II

***   ***   ***   ***   ***   ***   ***   ***   ***   ***  ***  ***   ***   *** 


COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS MEETING
APRIL 26, 2016 ADOPTION HEARING (WITHDRAWN: Request)
SMALL SCALE GROWTH MANAGEMENT PLAN AMENDMENT
HIBISCUS RESIDENTIAL INFILL SUBDISTRICT
PL20150002354/CPSS-2015-2


BCC ADOPTION ADVERTISEMENT:
As the advertisement appears in the Naples Daily News scheduled for April 06, 2016

BCC ADOPTION EXECUTIVE SUMMARY: 
PL20150002354/CPSS-2015-2

CCPC ADOPTION STAFF REPORT:
PL20150002354/CPSS-2015-2

ADOPTION ORDINANCE w/EXHIBIT “A’S”:
PL20150002354/CPSS-2015-2

PETITION:
PL20150002354/CPSS-2015-2

***   ***   ***   ***   ***   ***   ***   ***   ***   ***  ***  ***   ***   ***
 

Recommended by CCPC 6-0 on  3/17/2016 to forward to BCC 5/10/2016

COLLIER COUNTY PLANNING COMMISSION MEETING
SMALL SCALE GROWTH MANAGEMENT PLAN AMENDMENT
NAPLES BRIDGE CENTER - ADOPTION HEARING
PL20150002525/CPSS-2015-3 [companion CU-PL20150000873]

CCPC ADVERTISEMENT:
As it appeared in the Naples Daily News on 2/26/2016 


COMPLETE CCPC HEARING PACKET:
PL20150002525/CPSS-2015-3 - Part I & Part II

***   ***   ***   ***   ***   ***   ***   ***   ***   ***  ***  ***   ***   *** 

Recommended by CCPC on  2/18/2015 to forward to BCC 4/26/2016

COLLIER COUNTY PLANNING COMMISSION MEETING 
SMALL SCALE GROWTH MANAGEMENT PLAN AMENDMENT 
HIBISCUS RESIDENTIAL INFILL SUBDISTRICT - ADOPTION HEARING
PL20150002354/CPSS-2015-2 [companion PUDA-PL20150002326]


CCPC ADOPTION ADVERTISEMENT: 
As the advertisement appeared in the Naples Daily News on January 29, 2016.

COMPLETE CCPC HEARING PACKET:
PL20150002354/CPSS-2015-2 

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    
Department of Economic Opportunity (DEO) Cover Letter

Adopted - BCC 5-0 to transmit to the Department of Economic Opportunity (DEO)
Adopted Ordinance 2015-62

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS MEETING
NOVEMBER 10, 2015 – ADOPTION HEARING
SMALL SCALE GROWTH MANAGEMENT PLAN AMENDMENT
PL20140002143/CPSS-2014-4 
 

BCC ADOPTION ADVERTISEMENT:
As the advertisement appeared in the
Naples Daily News on October 21, 2015

BCC ADOPTION EXECUTIVE SUMMARY: 
PL20140002143/CPSS-2014-4

CCPC ADOPTION STAFF REPORT
:
PL20140002143/CPSS-2014-4

ADOPTION ORDINANCE w/EXHIBIT “A’S”:
PL20140002143/CPSS-2014-4

PETITION:
PL20140002143/CPSS-2014-4     

*** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** *** ***
COLLIER COUNTY PLANNING COMMISSION MEETING
ADVERTISED AUGUST 06, 2015 – ADOPTION HEARING
TO BE CONTINUED TO SEPTEMBER 03, 2015 BY APPLICANTS REQUEST
SMALL SCALE GROWTH MANAGEMENT PLAN AMENDMENT
PL20140002143/CPSS-2014-4
[companion PUDZ-PL20140002077]

CCPC ADOPTION ADVERTISEMENT:
As the advertisement appeared in the Naples Daily News on July 17, 2015.

COMPLETE CCPC HEARING PACKET:  
PL20140002143/CPSS-2014-4 

 ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***

Cover Letter to the Department of Economic Opportunity (DEO)
Approved Ordinance 2015-42

Adopted - BCC 5-0 to transmit to the Department of Economic Opportunity (DEO)


COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS MEETING
ADVERTISED FOR JULY 07, 2015 
ADOPTION HEARING - PL20140001282/CPSS-2014-2 SMALL SCALE
GROWTH MANAGEMENT PLAN AMENDMENT


BCC ADOPTION ADVERTISEMENT:

Advertisement as it shall appear in the Naples Daily News on June 17, 2015
PL20140001282/CPSS-2014-2 & Companion PUDZ-PL20140001326


BCC ADOPTION EXECUTIVE SUMMARY:
PL20140001282/CPSS-2014-2

CCPC ADOPTION STAFF REPORT:
PL20140001282/CPSS-2014-2

ADOPTION ORDINANCE w/EXHIBIT “A”:
PL20140001282/CPSS-2014-2

PETITION: 
PL20140001282/CPSS-2014-2


****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****         
Adopted - BCC 4-1 to transmit to the Department of Economic Opportunity (DEO)

Letter to Department of Economic Opportunity (DEO)

Adopted Ordinance #2015-32 
 

 

CONTINUED from April 28, 2015 to May 12, 2015, to: May 26, 2015 to
June 09, 2015:

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
APRIL 28, 2015 - GROWTH MANAGEMENT PLAN AMENDMENT
ADOPTION HEARING


BCC ADOPTION ADVERTISEMENT -
As advertised on April 8, 2015
PL20130001767/CP-2013-10 (w/companion PUDZ-PL20130001726)

BCC ADOPTION SUPPLEMENTAL EXECUTIVE SUMMARY:
PL20130001767/CP-2013-10

BCC ADOPTION EXECUTIVE SUMMARY:
PL20130001767/CP-2013-10

CCPC ADOPTION STAFF REPORT:
PL20130001767/CP-2013-10

DRAFT ORDINANCE w/Exhibit “A” TEXT & MAP:
PL20130001767/CP-2013-10

STATE AGENCY REVIEW COMMENTS:
PL20130001767/CP-2013-10

BCC TRANSMITTAL EXECUTIVE SUMMARY:
PL20130001767/CP-2013-10

CCPC TRANSMITTAL STAFF REPORT:
PL20130001767/CP-2013-10

TRANSMITTAL RESOLUTION w/Exhibit “A”:
2014-231

PETITION/APPLICATION: PL20130001767 (CP-2013-10)
The document being too large to upload to the website, may be viewed under
the Collier County Portal
:
http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #) only into the search area. Click “go”. Once open, click on “Planning Status” and then look to the bottom of the page for “Documents”. Click on the “>” and select “Documents”: then click on “BCC Hearing Packet”

****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****

Adopted - BCC 4-1 to transmit to the Department of Economic Opportunity (DEO)

Letter to Department of Economic Opportunity (DEO)

Adopted Ordinance #2015-29

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS MEETING
MAY 12, 2015 – ADOPTION HEARING
2014 CYCLE GROWTH MANAGEMENT PLAN AMENDMENT
PL20140000113/CP-2014-2


BCC ADOPTION ADVERTISEMENT:
As the advertisement appeared in the Naples Daily News on April 22, 2015

BCC ADOPTION EXECUTIVE SUMMARY:
PL20140000113/CP-2014-2

CCPC ADOPTION STAFF REPORT:
PL20140000113/CP-2014-2  

BCC ADOPTION ORDINANCE:
PL20140000113/CP-2014-2

REVIEW COMMENTS:
PL20140000113/CP-2014-2


BCC TRANSMITTAL EXECUTIVE SUMMARY:
PL20140000113/CP-2014-2


CCPC TRANSMITTAL STAFF REPORT:
PL20140000113/CP-2014-2

NIM AFFIDAVIT OF COMPLIANCE:
PL20140000113/CP-2014-2

ADOPTED TRANSMITTAL RESOLUTIONS w/EXHIBIT “A’s”:
PL20140000113/CP-2014-2

PETITION: PL20140000113/P-2014-2

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***     
CCPC Approved 5-0
Recommendation to BCC: Transmit to the Florida Department of Economic Opportunity (DEO)


COLLIER COUNTY PLANNING COMMISSION MEETING
MAY 07, 2015 – continued to MAY 21, 2015 - ADOPTION HEARING
SMALL SCALE GROWTH MANAGEMENT PLAN AMENDMENT
PL20140001282/CPSS-2014-2

BCC ADOPTION ADVERTISEMENT:  As the advertisement appeared in the Naples Daily News on April 17, 2014

CCPC ADOPTION STAFF REPORT:
PL20140001282/CPSS-2014-2

ADOPTION ORDINANCE: 
PL20140001282/CPSS-2014-2

PETITION:
PL20140001282/CPSS-2014-2

****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    
COLLIER COUNTY BOARD OF COUNTY COMMISSIOENRS
APRIL 14, 2015
GROWTH MANAGEMENT PLAN AMENDMENT
ADOPTION HEARING


Adopted - BCC 5-0 to transmit to the Department of Economic Opportunity (DEO)

Adoption Cover Letter to DEO 
 

Approved Ordinance 2015-26

BCC ADOPTION ADVERTISEMENT As advertised on February 28, 2015
PL20140000193/CPSS-2014-1 (w/companion PUDZ-PL20140000179)

EXECUTIVE SUMMARY:
PL20140000193/CPSS-2014-1

CCPC STAFF REPORT:
PL20140000193/CPSS-2014-1

DRAFT ORDINANCE w/EXHIBIT A TEXT AND MAP:
PL20140000193/CPSS-2014-1

PETITION: PL20140000193/CPSS-2014-1:
The document being too large to upload to the website, may be viewed under
the Collier County Portal:
http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #) only into the search area. Click “go”. Once open, click on “Planning Status” and then look to the bottom of the page for “Documents”. Click on the “>” and select “Documents”: then click on “BCC Hearing Packet”

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    

COLLIER COUNTY COLLIER COUNTY PLANNING COMMISSION
APRIL 02, 2015
GROWTH MANAGEMENT PLAN AMENDMENT
ADOPTION HEARING


CCPC Approved 4-0
Recommendation to BCC: Transmit to the Florida Department of Economic Opportunity (DEO)

CCPC ADOPTION ADVERTISEMENT As advertised on March 13, 2015
PL20140000113/CP-2014-2 (w/companion PUDZ-PL20130001726)


CCPC ADOPTION STAFF REPORT:
PL20140000113/CP-2014-2

DRAFT ADOPTION ORDINANCE w/EXHIBIT A TEXT AND MAP:
PL20140000113/CP-2014-2

BCC TRANSMITTAL EXECUTIVE SUMMARY:
PL20140000113/CP-2014-2

CCPC TRANSMITTAL STAFF REPORT:
PL20140000113/CP-2014-2

ADOPTED TRANSMITTAL RESOLUTION:
2014-262

PETITION PL20140000113/CP-2014-2:
The document being too large to upload to the website, may be viewed under
the
Collier County Portal:http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #) only into the search area. Click “go”. Once open, click on “Planning Status” and then look to the bottom of the page for “Documents”. Click on the “>” and select “Documents”: then click on “CCPC Hearing Packet”

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    

COLLIER COUNTY PLANNING COMMISSION
MARCH 19, 2015 - GROWTH MANAGEMENT PLAN AMENDMENT
ADOPTION HEARING


CCPC Vote: 5-0 (1 absent) Recommendation to BCC to Transmit to the Department of Ecomonic Opportunity (DEO)

CCPC ADOPTION ADVERTISEMENT - As advertised on February 27, 2015
PL20130001767/CP-2013-10 (w/companion PUDZ-30130001726)

CCPC ADOPTION STAFF REPORT:
PL20130001767/CP-2013-10

DRAFT ORDINANCE w/EXHIBIT A TEXT & MAP:
PL20130001767/CP-2013-10

STATE AGENCY REVIEW COMMENTS:
PL20130001767/CP-2013-10

BCC TRANSMITTAL EXECUTIVE SUMMARY:
PL20130001767/CP-2013-10

CCPC TRANSMITTAL STAFF REPORT:
PL20130001767/CP-2013-10

TRANSMITTAL RESOLUTION:
#2014-231

PETITION/APPLICATION: PL20130001767 (CP-2013-10):
The document being too large to upload to the website, may be viewed under
the Collier County Portal:
http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #) only into the search area. Click “go”. Once open, click on “Planning Status” and then look to the bottom of the page for “Documents”. Click on the “>” and select “Documents” then click on “CCPC Hearing Packet” 

 

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    

ADOPTED - BCC 5-0 to transmit to the Department of Economic Opportunity (DEO)

Adoption Letter to DEO

Adopted Ordinance #2015-22

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
MARCH 10, 2015 - GROWTH MANAGEMENT PLAN AMENDMENT
ADOPTION HEARING


BCC ADOPTION ADVERTISEMENT As advertised on February 18, 2015
PL20130001345/CP-2013-8 (w/companion PUDZ-20130001241)

ADOPTION EXECUTIVE SUMMARY: 
PL20130001345/CP-2013-8

ADOPTION CCPC STAFF REPORT:
PL20130001345/CP-2013-8

DRAFT ORDINANCE w/EXHIBIT A TEXT & MAP:
PL20130001345/CP-2013-8

STATE AGENCY REVIEW COMMENTS:
PL20130001345/CP-2013-8 

TRANSMITTAL EXECUTIVE SUMMARY:
PL20130001345/CP-2013-8

TRANSMITTAL CCPC STAFF REPORT:
PL20130001345/CP-2013-8

NIM MEETING MINUTES:
PL20130001345/CP-2013-8

TRANSMITTAL RESOLUTION:
2014-138

TRANSMITTAL STAFF-APPLICANT CORRESPONDENCE:
PL20130001345/CP-2013-8 

PETITION: PL20140000193/CPSS-2014-1:
The document being too large to upload to the website, may be viewed under
the Collier County Portal:
http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #) only into the search area. Click “go”. Once open, click on “Planning Status” and then look to the bottom of the page for “Documents”. Click on the “>” and select “Documents”: then click on “BCC Hearing Packet

****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    
 
COLLIER COUNTY PLANNING COMMISSION
FEBRUARY 19, 2015
GROWTH MANAGEMENT PLAN
SMALL SCALE AMENDMENT
ADOPTION HEARING


CCPC Vote: 6-0 Recommendation to BCC to Transmit to the Department of Ecomonic Opportunity (DEO)


CCPC ADOPTION ADVERTISEMENT As advertised on January 30, 2015
PL20140000193/CPSS-2014-1 (w/companion PUDZ-PL20140000179)

CCPC STAFF REPORT:
PL20140000193/CPSS-2014-1

& Neighborhood Information Meeting (NIM) Minutes :
PL20140000193/CPSS-2014-1 & Companion PUDZ-PL20140000179

DRAFT ORDINANCE w/EXHIBIT A TEXT AND MAP:
PL20140000193/CPSS-2014-1

PETITION: PL20140000193/CPSS-2014-1:
PL20140000193/CPSS-2014-1

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
FEBRUARY 10, 2015
GROWTH MANAGEMENT PLAN
SMALL SCALE AMENDMENT
ADOTION HEARING


ADOPTED - BCC 5-0 to transmit to the Department of Economic Opportunity (DEO)

Adoption Letter to DEO

Adopted Ordinance #2015-13  


BCC ADOPTION ADVERTISEMENT
- As advertised on January 21, 2015
PL20140000534/CPSS-2014-3 (w/companion PUDZ-20140000477)


EXECUTIVE SUMMARY:
PL20140000534/CPSS-2014-3

STAFF REPORT:
PL20140000534/CPSS-2014-3

DRAFT ORDINANCE w/EXHIBIT A TEXT & MAP:
PL20140000534/CPSS-2014-3

PETITION/APPLICATION: PL20140000534 (CPSS-2014-3)
The document being too large to upload to the website, may be viewed under
the
Collier County Portal:http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #) only into the search area. Click “go”. Once open, click on “Planning Status” and then look to the bottom of the page for “Documents”. Click on the “>” and select “Documents”: then click on “CCPC Hearing Packet”

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***  

 

 

ADOPTED - BCC 5-0 to transmit to the Department of Economic Opportunity (DEO) 
Adoption Letter to DEO & State Agencies

Adopted - Capital Improvement Element (CIE) Ordinance No. 2015-06, Conservation and Coastal Management Element (CCME) Ordinance No. 2015-07, Future Land Use Element (FLUE) Ordinance No. 2015-08, Public Facilities Element, Stormwater Sub-Element (SW) Ordinance No. 2015-9, Recreation & Open Space Element (ROSE) Ordinance No. 2015-10, and Transportation Element (TE) Ordinance No. 2015-11.


COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
JANUARY 27, 2014
GROWTH MANAGEMENT PLAN BATCH AMENDMENTS #1
ADOPTION HEARING


BCC ADOPTION ADVERTISEMENT -
As advertised on January 07, 2014
PL20130001109/CPSP-2013-6

ADOPTION EXECUTIVE SUMMARY:
PL20130001109/CPSP-2013-6

ADOPTION STAFF REPORT:
PL20130001109/CPSP-2013-6

REVIEW COMMENTS:
PL20130001109/CPSP-2013-6
  

DRAFT ORDINANCES w/EXHIBIT A TEXT & MAP:
CAPITAL IMPROVEMENT ELEMENT
CONSERVATION & COASTAL MANAGEMENT ELEMENT
FUTURE LAND USE ELEMENT
RECREATION AND OPEN SPACE ELEMENT
STORMWATER MANAGEMENT (DRAINAGE) SUBELEMENT OF THE PUBLIC FACILITIES ELEMENT
TRANSPORTATION ELEMENT

TRANSMITTAL EXECUTIVE SUMMARY:
PL20130001109/CPSP-2013-6

TRANSMITTAL STAFF REPORT:
PL20130001109/CPSP-2013-6

TRANSMITTAL EXECUTED RESOLUTION: 2014-153
PL20130001109/CPSP-2013-6 
  

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    

COLLIER COUNTY PLANNNIG COMMISSION
JANUARY 15, 2014
GROWTH MANAGEMENT PLAN AMENDMENT
ADOPTION HEARING

CCPC Vote: 6 - 0
Recommendation to the BCC to transmit to the Department of Economic Opportunity (DEO)

CCPC ADOPTION ADVERTISEMENTAs advertised on December 26, 2014
PL20130001345/CP-2013-8 (w/companion PUDZ-PL20130001241)

CCPC STAFF REPORT:
PL20130001345
/CP-2013-8

DRAFT ADOPTION ORDINANCE w/EXHIBIT A TEXT & MAP:
PL20130001345/CP-2013-8

REVIEW COMMENTS:
PL20130001345/CP-2013-8 

TRANSMITTAL EXECUTIVE SUMMARY:
PL20130001345/CP-2013-8

TRANSMITTAL STAFF REPORT:
PL20130001345/CP-2013-8

TRANSMITTAL NIGHT INFORMATION MEETING (NIM) MINUTES:
PL20130001345/CP-2013-8

EXECUTED TRAMSMITTAL RESOLUTION:
PL20130001345/CP-2013-8

PETITION: PL20140000193/CPSS-2014-1:
The document being too large to upload to the website, may be viewed under
the Collier County
Portal:http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #) only into the search area. Click “go”. Once open,
click on “Planning Status” and then look to the bottom of the page for “Documents”. Click on the “>” and select “Documents”: then click on “CCPC Hearing Packet” 

 

 

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***   ***    ***    ***    ***    ***    ***    ***    
COLLIER COUNTY PLANNING COMMISSION
DECEMBER 18, 2014 PL20140000534/CPSS-2014-3
GROWTH MANAGEMENT PLAN SMALL SCALE AMENDMENT
ADOPTION HEARING 

CCPC Vote:   5 - 0  
Recommendation to the BCC to transmit to the Department of Economic Opportunity
 

CCPC Adoption Advertisement - As advertised on November 26, 2014 -
PL20140000534/CPSS-2014-3

STAFF REPORT:
PL20140000534/CPSS-2014-3

DRAFT ORDINANCE w/EXHIBIT A TEXT & MAP:
PL20140000534/CPSS-2014-3

PETITION/APPLICATION: PL20140000534 (CPSS-2014-3)
The document being too large to upload to the website, may be viewed under
the Collier County Portal:
http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #) only into the search area. Click “go”. Once open, click on “Planning Status” and then look to the bottom of the page for “Documents”. Click on the “>” and select “Documents”: then click on “PL20140000534_CPSS-2014-3_Petition”

****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****       

COLLEIR COUNTY BOARD OF COUNTYCOMMISSIONERS
DECEMBER 09, 2014 PL20140000113/CP-2014-2 SAN MARINO
GROWTH MANAGEMENT PLAN AMENDMENT
TRANSMITTAL HEARING

ADOPTED - BCC 5-0 to transmit to the DEO
Transmittal Letter to DEO & State Agencies 

Adopted Resolution 2014-262

BCC Transmittal Advertisement - As advertised November 19, 2014
PL20140000113/CP-2014-2

EXECUTIVE SUMMARY:
PL20140000113/CP-2014-2

STAFF REPORT:
PL20140000113/CP-2014-2

NIM Affidavit of Compliance:
PL20140000113/CP-2014-2

 

DRAFT RESOLUTION w/EXHIBIT A TEXT & MAP
PL20140000113/CP-2014-2

PETITION/APPLICATION:
PL20140000113/CP-2014-2

****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****
CCPC Recommendation to BCC to adopt the petition 6-0 (M. Rosen absent):

COLLIER COUNTY PLANNING COMMISSION
DECEMBER 04, 2014 PL20130001109/CPSP-2013-6
GROWTH MANAGEMENT PLAN BATCH AMENDMENTS #1
ADOPTION HEARING


CCPC Adoption Advertisement - As advertised on November 14, 2014 
CPSP-2013-6

STAFF REPORT:
CPSP-2013-6

REVIEW RESPONSES:
CPSP-2013-6

DRAFT ADOPTION ORDINANCES w/EXHIBIT A TEXT & MAP: 
CIE ELEMENT
CCME ELEMENT
FUTURE LAND USE ELEMENT & FUTURE LAND USE MAP SERIES
RECREATON AND OPEN  SPACE ELEMENT
SANITARY SEWER SUBELEMENT OF THE PUBLIC FACILITIES ELEMENT
TRANSPORTATION ELEMENT
 
TRANSMITTAL EXECUTIVE SUMMARY:
CPSP-2013-6

TRANSMITTAL STAFF REPORT:
CPSP-2013-6

TRANSMITTAL EXECUTED RESOLUTION:
2014-153

****    ****    ****    ****    ****    ****    ****    ****    ****    ****    
ADOPTED - BCC 4-1 to transmit to the DEO 

Letter to DEO & State Agencies -
Approved Ordinance 2014-41

COLLEIR COUNTY BOARD OF COUNTY COMMISSIONERS
NOVEMBER 18, 2014 PL2011002626/CPS-2012-1
SMALL SCALE GROWTH MANAGEMENT PLAN AMENDMENT
ADOPTION HEARING

BCC Adoption Advertisement - As advertised on October 29, 2014
PL2011002626/CPSS-2012-1

EXECUTIVE SUMMARY:
PL20110002626/CPSS-2012-1

STAFF REPORT:
PL20110002626/CPSS-2012-1 

DRAFT ORDINANCE w/EXHIBIT A TEXT & MAP 
PL20110002626/CPSS-2012-1

PETITION/APPLICATION:
PL20110002626/CPSS-2012-1

STAFF CORRESPONDENCE:
PL20110002626/CPSS-2012-1

****    ****    ****    ****    ****    ****    ****    ****    ****    ****   ****    ****    ****

CCPC Recommendation to BCC to adopt the petition 7-0 w/changes:

To change Density referenced 2.5 DUs to 4 DUs, to 3.02 DUs per acre, with use of TDR credits coming from anywhere outside the current within 1 Mile of URF restriction.

COLLEIR COUNTY PLANNING COMMISSION
NOVEMBER 06, 2014 PL20140000113/CP-2014-2 SAN MARINO
GROWTH MANAGEMENT PLAN AMENDMENT
RANSMITTAL HEARING

CCPC Transmittal Advertisement - As advertised on October 17, 2014
PL20140000113/CP-2014-2

STAFF REPORT:
PL20140000113/CP-2014-2 -

DRAFT RESOLUTION w/EXHIBIT A TEXT as approved
PL20140000113/CP-2014-2 

PETITION/APPLICATION:
The document being too large to upload to the website, may be viewed under
the Collier County Portal:
http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #) only into the search area. Click “go”. Once open, click on “Project Application Review” and then look to the bottom of the page forDocuments”. Click on the “>” and select Documents”: then click on “PL20140000113/CP-2014-2 San Marino Petition”  

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
2013 CYCLE 3 GROWTH MANAGEMENT PLAN AMENDMENT

Advertised for October 14, 2014 -
CONTINUED to October 28, 2014
TRANSMITTAL HEARING


ADOPTED - BCC 4-1 to transmit to the DEO

Letter to DEO & State Agencies


BCC Transmittal Advertisement:
As appeared in the Naples Daily News on September 24, 2014

BCC TRANSMITTAL EXECUTIVE SUMMARY:
PL20130001767/CP-2013-10

CCPC TRANSMITTAL STAFF REPORT
PL20130001767/CP-2013-10

EXECUTED RESOLUTION w/Exhibit "A" Text and Table Changes (as revised)
PL20130001767/CP-2013-10 

PETITION/PROJECT: PL20130001767/CP-2013-10
PL20130001767-CP-2013-10

**** **** **** **** **** **** **** **** ****

COLLIER COUNTY PLANNING COMMISSION MEETING
GROWTH MANAGEMENT PLAN AMENDMENT ADOPTION HEARING
PL20110002626/CPSS-2012-1 SMALL SCALE

Advertised for July 17, 2014, continued to August 07, 2014,
and September 04, 2014, further continued to
Octobert 2, 2014

CCPC approved with recommendation to BCC to Transmit to the
Adoption Amendment to the Department of Economic Opportunity (DEO)

Advertisement: Continued from July 17, 2014 as advertised
PL20110002626/CPSS-2012-1

STAFF REPORT:
PL20110002626/CPSS-2012-1

DRAFT ORDINANCE w/EXHIBIT A TEXT & MAPS:
PL20110002626/CPSS-2012-1

PETITION/APPLICATION:
The document being too large to upload to the website, may be viewed under
the Collier County Portal
:
http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #’s only) into the search area. Click go”. Once open, click on “Project Application Review” and then look to the bottom of the page forDocuments”. Click on the “>” and selectDocuments”: then click on the appropriate CCPC Hearing Packet”

STAFF CORRESPONDENCE:
PL20110002626/CPSS-2012-1


****    ****    ****    ****    ****    ****    ****    ****    ****    ****
 
COLLIER COUNTY PLANNING COMMISSION MEETING
2013 CYCLE 3 GROWTH MANAGEMENT PLAN AMENDMENT
Advertised for August 21, 2014 and continue to September 4, 2014 
TRANSMITTAL HEARING

CCPC VOTE: 4-2 recommendation to BCC to transmit to the
D
epartment of Economic Opportunity (DEO)

BCC Transmittal Advertisement:
As appeared in the Naples Daily News on August 01, 2014

CCPC TRANSMITTAL STAFF REPORT:
PL20130001767/CP-2013-10

DRAFT RESOLUTION w/EXHIBIT “A’s”:
PL20130001767/CP-2013-10

PETITION/PROJECT:

PL20130001767/CP-2013-10
This document being too large to upload to the website, may be viewed under
the Collier County Portal:
http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #’s only) into the search area. Click “go”.
Once open click on “Project Application Review” and then look to the bottom of the
page for “Documents”. Click on the “>” and select “Documents”: then
click on
the
appropriate “CCPC Hearing Packet

****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****
COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS MEETING
JULY 08, 2014 – ADOPTION HEARING
2013 SMALL SCALE
GROWTH MANAGEMENT PLAN AMENDMENT

Transmittal Letter to DEO & State Agencies: 
PL20130002249/CPSS-2013-2

BCC approved Adoption Ordinance 5-0
PL20130002249/CPSS-2013-2 

BCC Adoption Advertisement: As appeared in the Naples Daily News on June 18, 2014
PL20130002249/CPSS-2013-2

BCC ADOPTION EXECUTIVE SUMMARY:
PL20130002249/CPSS-2013-2

CCPC ADOPTION STAFF REPORT:
PL20130002249/CPSS-2013-2

DRAFT ORDINANCE w/EXHIBIT A TEXT & MAP:
PL20130002249/CPSS-2013-2

PETITION: Project #PL20130002249 Internal #CPSS-2013-2

This document being too large to upload to the website, may be viewed under
the Collier County Portal:
http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #’s only) into the search area. Click “go”. Once open, click on “Project Application Review” and then look to the bottom of the
page for “Documents”. Click on the “>” and select “Documents”: then click on
the appropriate “Hearing Packet”


***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS MEETING
JULY 08, 2014 –TRANSMITTAL HEARING
2013 BATCH #1 IN-HOUSE GROWTH MANAGEMENT PLAN AMENDMENTS


Transmittal Letter to DEO & State Agencies:
 PL20130001109/CPSP-2013-6

BCC approved Transmittal Resolution 5-0
PL20130001109/CPSP-2013-6 

BCC Transmittal Advertisement: As appeared in the Naples Daily News on June 18, 2014
PL20130001109/CPSP-2013-6

BCC TRANSMITTAL EXECUTIVE SUMMARY:
PL20130001109/CPSP-2013-6

CCPC TRANSMITTAL STAFF REPORT:
PL20130001109/CPSP-2013-6

DRAFT RESOLUTION w/EXHIBIT A TEXT/MAP CHANGES:
PL20130001109/CPSP-2013-6      

 

 

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS MEETING
JUNE 24, 2014 – TRANSMITTAL HEARING
2013 CYCLE 2 GROWTH MANAGEMENT PLAN AMENDMENTS


Transmittal Letter to DEO & State Agencies:
PL20130001345/CP-2013-8

BCC Approved Transmittal Resolution: 5-0
PL20130001345/CP-2013-8

BCC Transmittal Advertisement: As appeared in the Naples Daily News on June 04, 2014
PL20130001345/CP-2013-8

BCC TRANSMITTAL EXECUTIVE SUMMARY:
PL20130001345/CP-2013-8

CCPC TRANSMITTAL STAFF REPORT:
PL20130001345/CP-2013-8

DRAFT RESOLUTIONS w/EXHIBIT “A’s”:
PL20130001345/CP-2013-8

PETITION: PL20130001345/CP-2013-8:
These documents being too large to upload to the website, may be viewed under
the Collier County Portal:
http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #’s only) into the search area. Click “go”. Once open, click on “Project Application Review” and then look to the bottom of the
page for “Documents”. Click on the “>” and select “Documents”: then
click on
the appropriate “Hearing Packet”
 
 

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***     

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS MEETING
JUNE 10, 2014 – ADOPTION HEARING
2013 CYCLE 1 GMP AMENDMENTS 

Adoption Approval Letter to the Department of Economic Opportunity (DEO)

BCC Approved Ordinances:
PL20130000139/CP-2013-1
PL20120002909/CP-2013-3
PL20130000365/CP-2013-4

BCC Action:
PL20130000139/CP-2013-1: Commission Vote 4-1 to transmit to the DEO
PL20120002909/CP-2013-3: Commission Vote: 5-0 to transmit to the DEO
PL20130000365/CP-2013-4: Commission Vote: 5-0 to transmit to the DEO

BCC ADOPTION Advertisement(s): As they appeared in the Naples Daily News
on May 21, 2014:
PL20130000139/CP-2013-1; PL20120002909/CP-2013-3 & companion PUDZ-PL20120002906; PL20130000365/CP-2013-4 & companion PUDZ-A-PL20130001374 

BCC ADOPTION Executive Summary(s):

PL20120002909_CP-2013-3/PL20130000139_CP-2013-1 &

PL20130000365_CP-2013-4

CCPC ADOPTION Staff Report:
PL20130002909_CP-2013-3; PL20130000139_CP-2013-1/PL20130000365_CP-2013-4

DRAFT ADOPTION Ordinances w/Exhibit “A’” attached: 

PL20130000139/CP-2013-1; and 

PL20120002909/CP-2013-3;

PL20130000265/CP-2013-4 

Projects:

PL20120002909 for Petition #CP-2013-3;
PL20130000139 for Petition #CP-2013-1; &
PL20130000365 for Petition #CP-2013-4


These documents being too large to upload to the website, may be viewed under
the Collier County Portal:
http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing the project number (SEE ABOVE PL #’s only) into the search area. Click “go”. Once open, click on “Project Application Review” and then look to the bottom of the
page for “Documents”. Click on the “>” and select “Documents”: then click on
the appropriate “Hearing Packet”

****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    
COLLIER COUNTY PLANNING COMMISSION MEETING
JUNE 05, 2014 – BCC CHAMBER 
CONTINUED FROM APRIL 17, 2014 & MAY 15, 2014
PL20130002249/CPSS-2013-2 SMALL SCALE GMP AMENDMENT ADOPTION 

PL20130002249.CPSS-2013-2 CCPC Vote: 7-0 Recommendation to BCC Approval w/changes

Naples Daily News Advertisement as it appeared on March 28, 2014:

PL20130002249.CPSS-2013-2

CCPC ADOPTION STAFF REPORT:
PL20130002249/CPSS-2013-2

DRAFT ADOPTION ORDINANCE:  
PL20130002249/CPSS-2013-2

EXHIBIT ‘A’ TEXT CHANGES:
PL20130002249/CPSS-2013-2

EXHIBIT ‘A’ MAP CHANGES:
PL20130002249/CPSS-2013-2

PETITION:
PL20130002249/CPSS-2013-2 

 ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****
(5-0 recommendation to transmit to DEO)
COLLIER COUNTY PLANNING COMMISSION MEETING
MAY, 15, 2014 - BCC CHAMBER
2013 BATCH #1 GMP AMENDMENTS - TRANSMITTAL
 
      
 

PL20130001109/CPSP-2013-6  CCPC Vote: 5-0 to transmit to the DEO

Naples Daily News Advertisement as it appeared April 11, 2014
PL20130001109/CPSP-2013-6

TRANSMITTAL CCPC STAFF REPORT: 
PL20130001109/CPSP-2013-6

TRANSMITTAL ‘DRAFT’ RESOLUTION:
PL20130001109/CPSP-2013-6

TRANSMITTAL EXHIBIT ‘A’ TEXT CHANGES: [See above attachment to Resolution for:
Capital Improvement Element; Transportation Element; Conservation and Coastal Improvement
Element; Recreation and Open Space Element; Future Land Use Element; and Stormwater
Management (Drainage) Sub Element of the Public Facilities Element]

****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****

COLLIER COUNTY PLANNING COMMISSION MEETING - IN BCC CHAMBER 
2013 CYCLE 1 GMP ADOPTION AMENDMENTS
(
PL20120002909/CP-2013-3 ONLY CONTINUED TO MAY 15, 2014
FROM THE MAY 01, 2014 CCPC)
 

PL20130000139/CP-2013-1 CCPC Vote:
7-0 to transmit to the DEO
PL20120002909/CP-2013-3 CCPC Vote: 5-1 to transmit to the DEO
PL20130000365/CP-2013-4 CCPC Vote: 6-0 to transmit to the DEO


Advertisements as they appeared on April 11, 2014
 
PL20130000139/CP-2013-1; and 

PL20120002909/CP-2013-3; and

PL20130000365/CP-2013-4

CCPC ADOPTION STAFF REPORT: 

PL20130000139/CP-2013-1, and PL20120002909/CP-2013-3, and PL2013000036/CP-2013-4

“DRAFT” ORDINANCES:
PL20130000139/CP-2013-1;  
PL20120002909/CP-2013-3; 
PL20130000365/CP-2013-4  

EXHIBIT ‘A’ TEXT CHANGES: CCPC Consent Agenda changes:
PL20120002909/CP-2013-3

PL20120002909/CP-2013-3; (w/above changes final)

PL20130000365/CP-2013-4

EXHIBIT ‘A’ MAP CHANGES:

PL20130000139/CP-2013-1

TRANSMITTAL EXECUTIVE SUMMARY:

PL20130000139/CP-2013-1, and PL20120002909/CP-2013-3, and PL20130000365/CP-2013-4

TRANSMITTAL STAFF REPORTS: 

PL20130000139/CP-2013-1; and 

PL20120002909/CP-2013-3; and 

PL20130000365/CP-2013-4

EAC TRANSMITTAL STAFF REPORT:

PL20130000365/CP-2013-4

PETITIONS:

PL20130000139/CP-2013-1

PETITIONS: #PL20120002909 (Petition CP-2013-3) & #PL20130000364 (Petition CP-2013-4) PART 1
AND PL20130000365 (Petition CP-2013-4) PART 2:


These documents being too large to upload to the website, may be viewed under
the Collier County Portal:
http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing this project (SEE ABOVE #PL) into the search area. Click “go”. Once open,
click on “Project Application Review” and then look to the bottom of the
page for “Documents”. Click on the “>” and select “Documents”: then click on
“PL201220002909/CP-2013-3 OR PL20130000365/CP-2013-4 Hearing Packet.” 

****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    ****    
COLLIER COUNTY PLANNING COMMISSION MEETINGAPRIL 29, 2014 –
SPECIAL CCPC MEETING
710 IMMOKALEE DRIVE, IMMOKALEE, FL., 34143
PL20130001345/CP-2013-8 GMP AMENDMENT TRANSMTTAL


PL20130001345/CP-2013-8 CCPC Vote: 7-0 to Transmit to the DEO 

Naples Daily News Advertisement as it appeared on April 09, 2014:
PL20130001345.CP-2013-8 

TRANSMITTAL "SPECIAL" AGENDA
CCPC Agenda

 

 

TRANSMITTAL CCPC STAFF REPORT:
PL20130001345/CP-2013-8 

TRANSMITTAL ‘DRAFT’ RESOLUTION:
PL20130001345/CP-2013-8

TRANSMITTAL EXHIBIT ‘A’ TEXT CHANGES:
PL20130001345/CP-2013-8

TRANSMITTAL EXHIBIT ‘A’ MAP CHANGES:
PL20130001345/CP-2013-8

STAFF/APPLICANT CORRESPONDENCE:
PL20130001345/CP-2013-8

PETIITION: This document being too large to upload to the website, may be viewed under
the Collier County Portal:
http://cvportal.colliergov.net/CityViewWeb/Planning/Locator
by placing this project # PL20130001345 into the search area. Click “go”.
Once open,
click on “Project Application Review” and then look to the bottom of the page for “Documents”. Click on the “>” and select “Documents”: then click on
“PL20130001345/CP-2013-8 CCPC Hearing Packet.” 

***     ***     ***     ***     ***     ***     ***     ***     ***     ***     ***     ***     ***     ***     ***     ***     ***     ***
    

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS MEETING
APRIL 22, 2014 - BCC CHAMBER
10 YEAR WATER FACILITIES SUPPLY PLAN
PL201300001132/CPSP-2013-7 GMP AMENDMENT ADOPTION

Naples Daily News Advertisement as it appeared on April 02, 2014: 
PL20130001132/CPSP-2013-7

BCC ADOPTION EXECUTIVE SUMMARY:
PL20130001132/CPSP-2013-7

CCPC ADOPTION STAFF REPORT:
PL20130001132/CPSP-2013-7

10 YEAR WATER SUPPLY PLAN:
PL20130001132/CPSP-2013-7

DEPARTMENT OF ECONOMIC OPPORTUNITY ORC REPORT:
Objections, Recommendations and Comments Report

ADOPTION ORDNINANCE & EXHIBIT 'A' DRAFT: 
PL20130001132/CPSP-2013-7 Ordinance - Exhibit "A" Text Changes

BCC TRANSMITTAL EXECUTIVE SUMMARY:
PL20130001132/CPSP-2013-7

CCPC TRANSMITTAL STAFF REPORT:
PL20130001132/CPSP-2013-7

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***   
COLLIER COUNTY PLANNING COMMISSION MEETING
MARCH 06, 2014 - BCC CHAMBER
PL201300001132/CPSP-2013-7 ADOPTION GMP AMENDMENT


Naples Daily News Advertisement as it appeared on February 14, 2014:
PL20130001132/CPSP-2013-7

CCPC ADOPTION STAFF REPORT: 
PL20130001132/CPSP-2013-7

10 YEAR WATER SUPPLY PLAN - DRAFT: 
PL20130001132/CPSP-2013-7

DEPARTMENT OF ECONOMIC OPPORTUNITY ORC REPORT:
Objections, Recommendations and Comments Report

ADOPTION ORDNINANCE & EXHIBIT 'A' DRAFT: 
PL20130001132/CPSP-2013-7 Ordinance - Exhibit "A" Text Changes

BCC TRANSMITTAL EXECUTIVE SUMMARY:
PL20130001132/CPSP-2013-7

CCPC TRANSMITTAL STAFF REPORT:
PL20130001132/CPSP-2013-7

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***   ***   

COLLER COUNTY BOARD OF COUNTY COMMISSIONERS
MEETING NOVEMBER 12, 2013 - ADOPTED BCC 
TO TRANSMIT TO THE DEPARTMENT OF ECONOMIC OPPORTUNITY, THE
2013 CYCLE 1 TRANSMITTAL GROWTH MANAGEMENT PLAN AMENDMENTS
 

2013 Cycle 1 DEO Letter of Acknowledgement

Department of Economic Opportunity (DEO) Cover Letter
  

Adopted Transmittal Resolutions:

 

 

Resolution 13-264 CP-2013-1  

Resolution 13-265 CP-2013-4

Resolution 13-266 CP-2013-3 

 ***    ***    ***    ***    ***    ***    ***    **    ***    ***    ***    ***    

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
2013 CYCLE 1 GMP AMENDMENTS
NOVEMBER 12, 2013
  

BCC TRANSMITTAL ADVERTISEMENT: 
As appeared in the Naples Daily News on October 23, 2013 

BCC TRANSMITTAL EXECUTIVE SUMMARY:

PL20130000139/CP-2013-1 & PL20120002909/CP-2013-3 & PL20130000365/CP-2013-4

Supplement (Davidson Engineering) to PL20120002909/CP-2013-3 

BCC TRANSMITTAL TABLE OF CONTENTS:
Table of Contents


BCC TRANSMITTAL GMP RESOLUTIONS:

 

 

PL20130000139/CP-2013-1
Application Text

Exhibits A-1, B, C, D   

PL20120002909/CP-2013-3
Application

Staff Correspondence
Sufficiency Letter

Substantive Review Letter

PL20130000365/CP-2013-4

AHC TECHNICAL REPORT No. 982

GMP Amendment Exhibit List

Sufficiency Response Ltr 4-25-13

Cover Letter dated 02-22-13

Revised GMP Amendment Application

Exhibit A Location Map

Exhibit B Recent Aerial

Exhibit C Existing FLU

Exhibit D Proposed FLU

Exhibit E FLUCCS & Native Habitat Acreage

Exhibit F Soils

Exhibit G Listed Species Summary Table

Exhibit G-1 Listed Spec Survey 2008

Exhibit G-2 SFWMD 1990 Wetland Det

Exhibit G-3 SFWMD 1992 Wetland Det

Exhibit G-4 SFWMD 2010 Wetland Det  

Exhibit G-8 Current Site Conditions

Exhibit H Arch Map   

Exhibit H-1 Archaeological Summary  

Exhibit I-1 thru I-4 Pub Facility  Report           

Exhibit I-5 Utility Availability Map

 

Exhibit I-6 FIRM Data Map

Exhibit I-7 Location of Wells & Cones of Influence

Exhibit I-8 Locations of Wells & Cones of Infl

Exhibit J TIS Appendix A

Exhibit J TIS

Exhibit J-1 Intersection Analysis

Exhibit K Deeds

Exhibit L List of Owners

***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***
COLLIER COUNTY PLANNING COMMISSION
2013 CYCLE 1 GMP AMENDMENTS
SEPTEMBER 19, 2013
   
 

CCPC Transmittal Advertisement: 
As appeared in the Naples Daily News on August 30, 2013

CCPC STAFF REPORT(S):

PL20130000139/CP-2013-1

PL20120002909/CP-2013-3             

 



P
L20130000365/CP-2013-4

DRAFT TRANSMITTAL RESOLUTION(S):

PL20130000139/CP-2013-1

PL20120002909/CP-2013-3

PL20130000365/CP-2013-4

EXHIBIT "A" TEXT CHANGES:
PL20130000139/CP-2013-1 
PL20120002909/CP-2013-3

EXHIBIT "A" MAP CHANGES:

 

   PL20130000365/CP-2013-4

***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***   ***  ***   ***   ***   ***    

ENVIRONMENTAL ADVISORY COUNCIL (EAC) MEETING 
AUGUST 07, 2013 in BCC CHAMBER

PETITION: PL20130000365/CP-2013-4 
STAFF REPORT   

***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***

COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
2012 CYCLE GMP 'ADOPTION' AMENDMENTS
MAY 28, 2013
 
      

DEO FINDING OF COMPLIANCE: Letter dated June 20,2013

EXECUTED ORDINANCES AS RECEIVED FROM THE STATE OF FLORIDA:
2013-41 GORDON RIVER GREEN PARK2013-42 BAYSHORE/GATEWAY CRA 

DEO RECEIPT OF 2012 CYCLE ADOPTION AMENDMENTS:
13-2ESR

DEPARTMENT OF ECONOMIC OPPORTUNITY (DEO) SUBMITTAL: COVER LETTER 

Approved by the Board of County Commissioners on 5/28/2013
4-0 (Commissioner Hillar absent)


PL20120000371/CP-2013-1 

 

PL20120001213/CP-2013-3

BCC 2012 Cycle Adoption Advertisement:
As it appeared on May 08, 2013    

BCC ADOPTION EXECUTIVE SUMMARY:
 
PL20120000371/CP-2012-1 & PL20120001213/CP-2012-3

BCC ADOPTION ORDINANCES, including BCC ADOPTION EXHIBIT "A" changes:
PL20120000371/CP-2012-1 
PL20120001213/CP-2012-3
---    ---    ---    ---    ---    ---    ---    ---    ---    ---    ---    ---    ---    ---    ---    ---    ---    ---    ---
COLLIER COUNTY PLANNING COMMISSION 
2012 CYCLE GMP ADOPTION AMENDMENTS 
APRIL 04, 2013 & MAY O2, 2013
PETITION PL20120001213/CP-2012-3 ONLY
CONTINUED TO MAY 02, 2013: 

CCPC 2012 Cycle Adoption Advertisement:
As it appeared in the Naples Daily News on March 15, 2013

CCPC Adoption Staff Report: 
PL20120000371/CP-2012-1 & PL20120001213/CP-2012-3

CCPC ADOPTION ORDINANCES:

PL20120000371/CP-2012-1 - APPROVED 7-0 RECOMMENDATION TO BCC TO
TRANSMIT TO THE DEPARTMENT OF ECONOMIC OPPORTUNITY (DEO)

PL20120001213/CP-2012-3 - APPROVED 6-0 RECOMMENDATION TO BCC TO
TRANSMIT TO THE DEPARTMENT OF ECONOMIC OPPORTUNITY (DEO)

PL20120000371/CP-2012-1 - APPROVED 7-0 RECOMMENDATION TO BCC TO
TRANSMIT TO THE DEPARTMENT OF ECONOMIC OPPORTUNITY (DEO) 

PL20120001213/CP-2012-3 - APPROVED 6-0 RECOMMENDATION TO BCC TO
TRANSMIT TO THE DEPARTMENT OF ECONOMIC OPPORTUNITY (DEO)
-  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -  -
 

COLLER COUNTY BOARD OF COUNTY COMMISSIONERS
MEETING JANUARY 08, 2013 - ADOPTED BCC 5-0
TO TRANSMIT TO THE DEPARTMENT OF ECONOMIC OPPORTUNITY, THE
2012 CYCLE TRANSMITTAL GROWTH MANAGEMENT PLAN AMENDMENTS
 

2012 Cycle DEO Letter of Acknowledgement 

Department of Economic Oppportunity (DEO) Cover Letter

Adopted Transmittal Resolutions: 
Resolution 2013-13: PL20120000371/CP-2012-1 

Resolution 2012-14: PL20120001213/CP-2012-3 

BCC 2012 Cycle Transmittal Advertisement: 
As appeared in the Naples Daily News on 12/19/2012             

BCC Transmittal Executive Summary:
PL20120000371/CP-2012-1 & PL20120001213/CP-2012-3

 

TRANSMITTAL GMP RESOLUTIONS including Exhibit "A" Text and/or Map: 
PL20120000371/CP-2012-1

PL20120001213/CP-2012-3

STAFF REPORTS: 
PL20120000371/CP-2012-1

PL20120001213/CP-2012-3 

***       ***        ***        ***    ***        ***        ***        ***        ***        *** 

 

COUNTY PLANNING COMMISSION MEETING
CONTINUED FROM: September 20, 2012 TO: November 01, 2012 (AGENDA ITEM 9A)
SMALL SCALE GROWTH MANAGEMENT PLAN ADOPTION AMENDMENT

CCPC Hearing Results: 7-1 (Ebert) Recommendation to BCC to Transmit to the Department of Economic Opportunity (DEO)

CCPC/BCC SIGN POSTING: (requirements met)
 
Sign Post #1 Photo Proof

Sign Post #2 Photo Proof

Naples Daily News CCPC Advertisement:   Post Date 8/31/2012   

CCPC STAFF REPORT:
Project PL20110000769/Petition CPSS_2011-2

CCPC ADOPTION ORDINANCE:
Project PL20110000769/Petition CPSS_2011-2

CCPC EXHIBIT "A" TEXT CHANGES:
Project PL20110000769/Petition CPSS_2011-2

CCPC EXHIBIT "A" MAP CHANGES:
Golden Gate Area Master Plan Future Land Use Map

Golden Gate Urban Commercial Infill Subdistrict and Golden Gate Estates Commercial
and Insitutional Infill Subdistrict


***    ***    ***    ***    ***    ***    ***    ***    ***    ***    ***
COLLIER COUNTY PLANNING COMMISSION MEETING
November 01, 2012
2012 CYCLE GROWTH MANAGEMENT PLAN TRANSMITTAL AMENDMENTS
AGENDA ITEMS 9B AND 9C

CCPC Hearing Results: Both items - 8-0 Recommendation to BCC to Transmit to the Department of Economic Opportunity (DEO)

CCPC 2012 Cycle Transmittal Advertisement as appeared in the Naples Daily News 10/12/2012

TRANSMITTAL GMP RESOLUTIONS: 
PL20120000371/CP-2012-1 
PL20120001213/CP-2012-3

STAFF REPORTS: 
PL20120000371/CP-2012-1
PL20120001213/CP-2012-3 

EXHIBIT “A” (draft) TEXT: 
PL20120001213/CP-2012-3

EXHIBIT “A” (draft) MAP: 
PL20120000371/CP-2012-1 

***     ***     ***     ***     ***     ***      ***     ***     ***     ***     ***     ***     ***     ***     ***     ***     ***     *** 
BOARD OF COUNTY COMMISSIONERS
MEETING APRIL 24, 2012
FOR A SMALL SCALE GROWTH MANAGEMENT PLAN AMENDMENT 
AMENDING THE FUTURE LAND USE ELEMENT (FLUE)
"ORANGE BLOSSOM/AIRPORT CROSSROADS COMMERCIAL SUBDISTRICT"
PROJECT #PL20110002601, PETITION #CPSS-2011-1 

With a vote "5-0" the Board of County Commissioners (BCC)
approved the Adoption Small Scale Amendment submitting to the:
Florida Department of Economic Opportunity

Department of Economic Opportunity (DEO)
Submittal Response/Approval

Department of Economic Opportunity "DEO" Cover Letter 

As Transmitted: Ordinance #2012-16

BCC ADVERTISMENT:  CPSS-2011-1 [Project #20110002601]

Naples Daily News Advertisement - Post Date 4/04/2012  

CCPC/BCC Sign Posting - 15 days prior to CCPC Meeting (requirements met):
Photo #1; Photo #2 and Photo #3


BCC EXECUTIVE SUMMARY:
CPSS-2011-1 [Project #20110002601]

CCPC STAFF REPORT:
CPSS-2011-1 [Project #20110002601]

ADOPTION ORDINANCE:
CPSS-2011-1 [Project #20110002601]

EXHIBIT "A' TEXT CHANGES:
CPSS-2011-1 [Project #20110002601]

LOCATION MAP:
CPSS-2011-1 [Project #20110002601]

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
COLLIER COUNTY PLANNING COMMISSION MEETING
MARCH 01, 2012
SMALL SCALE AMENDMENT
AMENDING THE FUTURE LAND USE ELEMENTS (FLUE) 
ORANGE BLOSSOM/AIRPORT CROSSROADS COMMERCIAL SUBDISTRICT
PROJECT #PL20110002601, PETITION #CPSS-2011-1 

CCPC Recommendation to the BCC to approve the following on 3/06/2012 -
7-0
(Brad Schiffer and Paul Midney absent)

CCPC SPECIAL: Public Notice Memo - Continued from 3/01/2012 to 3/06/2012 - Post Date 3/02/3012

CCPC ADVERTISMENT:  CPSS-2011-1 [Project #20110002601]

Naples Daily News Advertisement - Post Date 2/10/2012 & Public Notice Memo - Post Date 2/16/2012

CCPC/BCC Sign Posting (15 days prior to CCPC Meeting)
Photo #1; Photo #2 and Photo #3

CCPC STAFF REPORT:
CPSS-2011-1 [Project #20110002601]

ADOPTION ORDINANCE:
CPSS-2011-1 [Project #20110002601] 

EXHIBIT "A' TEXT CHANGES:
CPSS-2011-1 [Project #20110002601]

LOCATION MAP:
CPSS-2011-1 [Project #20110002601]

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

WITHDRAWN PETITIONS:

CP-2014-3 ROCKEDGE
GROWTH MANAGEMENT PLAN AMENDMENT

CP-2009-2 BIG ISLAND EXCAVACTION
GROWTH MANAGEMENT PLAN AMENDMENT

CP-2012-2 TOP HAT AUTO
GROWTH MANAGEMENT PLAN AMENDMENT

CP-2009-1 DADE-COLLIER CYPRESS RECREATIONAL PARK
GROWTH MANAGEMENT PLAN AMENDMENT

CPSS-2008-1 TRADEPORT/IMMOKALEE
SMALL SCALE GROWTH MANAGEMENT PLAN AMENDMENT

CP-2008-3 GOLDEN GATE PARKWAY MIXED USE SUBDISTRICT
GROWTH MANAGEMENT PLAN AMENDMENT

CP-2007-5 LOGAN/IMMOKALEE COMMERCIAL SUBDISTRICT
GROWTH MANAGEMENT PLAN AMENDMENT

CP-2007-4 EXPANSION A/C #18
GROWTH MANAGEMENT PLAN AMENDMENT

CP-2007-2 IMMOKALEE/OIL WELL ROADS COMMERCIAL SUBDISTRICT
GROWTH MANAGEMENT PLAN AMENDMENT

CP-2007-1 WILSON BOULEVARD COMMERCIAL SUBDISTRICT
GROWTH MANAGEMENT PLAN AMENDMENT

CP-2006-9 RLSA OPEN TO HSA DESIGNATION
GROWTH MANAGEMENT PLAN AMENDMENT

CPSS-2016-1 ORANGE BLOSSOM/AIRPORT CROSSROADS COMERCIAL SUBDISTRICT
GROWTH MANAGEMENT PLAN AMENDMENT

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer